LEGEND MAP FOR REFERENCE



Click on above picture to see larger version of it.

Please refer to the above map to see what section of the plant is currently being pile driven during this cycle. The letters for each section are found on the piling schedule maps below.


Quick Jump to Area:
Click on link in this area to quick jump to a "Pile Driving Area"

Area 1 - Main Headworks Building - Section A
Area 2 - Oxidation Ditch - Section B
Area 3 - Oxidation Ditch Pumping Station - Section C
Area 4 - Final Settling Tank #1 - Section D
Area 5 - Final Settling Tank #2 - Section D


Great Neck Water Pollution Control District
Pile Driving Status Maps

 
........
.LEGEND TO COLORS ON MAPS BELOW:

  This Pile is Scheduled to be Driven
  Pile Driving of this pile has been completed
....
TBD = Still To Be Determined
 


Piling Area 1 - Main Headworks Building
Click on above picture to see larger version of drawing

This Area has Been Fully Completed


Pile Driving start date for Area 1-Main Headworks Building was:
June 15, 2011


Number of Piles to be driven in total for Area 1 was:
29
Number of Piles that have to date been driven in Area 1:
29
Number of Piles Still to Be Driven in Area 1:
0


Pile Driving here was completed on:

June 20, 2011



Piling Area 2 - Oxidation Ditch

Click on above picture to see larger version of drawing

Piling is Currently Underway in this Area

The Initial test Pile Driving in this area that was performed, was completed in late September of 2011. The regular planned pile driving is now commencing in full due to the test pile driving being having been successful prior.



Start and Completion of initial testing for Pile Driving for Area 2 was:
September 28, 2011
Regularly Scheduled Pile Driving start date for the Pile Driving Work in Area 2 was:
November 8, 2011


Number of Piles to be driven in total for Area 2 is:
468
Number of Piles that have to date been driven in Area 2:
171
Number of Piles Still to Be Driven in Area 2:
297


Pile Driving here will be/was fully completed on:
TBD


Piling Area 3 - Oxidation Ditch Pumping Station

Click on above picture to see larger version of drawing

???
The Piling in this Area Hasn't Started as of Yet



Scheduled Pile Driving start date for this area is:
TBD


Number of Piles to be driven in total for Area 3 is:
22
Number of Piles that have to date been driven in Area 3:
0
Number of Piles Still to Be Driven in Area 3:
22


Pile Driving here will be/was completed on:
TBD


Piling Area 4 - Final Settling Tank #1

Click on above picture to see larger version of drawing

???
The Piling in this Area Hasn't Started as of Yet



Scheduled Pile Driving start date for this area is:
TBD


Number of Piles to be driven in total for Area 4 is:
107
Number of Piles that have to date been driven in Area 4:
0
Number of Piles Still to Be Driven in Area 4:
107


Pile Driving here will be/was completed on:
TBD

Piling Area 5 - Final Settling Tank #2

Click on above picture to see larger version of drawing

???
The Piling in this Area is Currently Paused

The Initial test Pile Driving in this area that was performed, has ceased for now. The regular pile driving to be performed here will be continued at a still to be determined date.

Upon knowledge of that date, it will be posted here.



Test Pile Driving start and completed date for Area 5 was:
September 28, 2011
Scheduled Pile Driving start date for Continuing Work in Area 5 is:
TBD


Number of Piles to be driven in total for Area 5 is:
107
Number of Piles that have to date been driven in Area 5:
1
Number of Piles Still to Be Driven in Area 5:
106


Pile Driving here will be/was completed on:
TBD

Stay tuned for more up to date additions.

This section of the site will be updated daily as the work gets completed or more areas are added. Please bookmark and check back often to see how far along the process is coming.